KEY POINTS
- COP31 in Antalya ended without a pact after the EU, the UK and several vulnerable nations rejected the draft as too weak.
- Only voluntary pledges on electrification and on AI data centers emerged, and the AI pledge drew little support.
- Meta said it is re-evaluating its net zero timeline after reporting a 45 percent year-over-year rise in climate pollution.
The United Nations climate conference COP31 ended in Antalya, Turkey, on Sunday without an agreed pact, and the surge in AI data centers was one of the issues that complicated the talks, The Verge reported. The summit ran two days past its schedule, making it the longest COP so far.
Delegates had spent two weeks bargaining over a deal that the EU, the UK and several of the countries most exposed to climate change rejected as too weak. According to The Verge, the text left out the term "fossil fuels" even though many nations wanted firmer commitments to phase out oil, coal and gas. The United States, home to the largest data center buildout, did not attend after the Trump administration withdrew from the Paris accord.
One of the most watched goals was raising electricity's share of global energy use to 35 percent by 2035, from about 20 percent now. Growing data center demand makes that harder. Chris Bowen, Australia's climate and energy minister, who leads the negotiations, told Politico that every climate minister is thinking about the issue and that it would inevitably come up.
With formal talks stalled, countries made only voluntary commitments. About 80 nations signed a pledge on the 35 percent electrification target, according to COP31 president Murat Kurum, although Carbon Brief reported that the list of signatories had not yet been published. A separate pledge asking data centers to use less polluting energy attracted little support.
Bruce Douglas, CEO of the Global Renewables Alliance, told The Verge by email that the pledge's wording on "low-emission energy" could still allow natural gas to power data centers. He said data centers are often outbidding other users for grid connections, financing and generating capacity. The Natural Resources Defense Council called the pledge a step in the right direction but said it needs stronger enforcement.
Tech companies' own targets are also under pressure. Meta said in its annual sustainability report on Thursday that it is re-evaluating its timeline for net zero emissions as it focuses on AI, and it reported a 45 percent year-over-year increase in climate pollution. The Verge noted that the carbon footprints of Google and Microsoft are also growing despite their climate commitments.
Forecasts point to further growth. The International Energy Agency expects data center electricity use to double by 2030. A Sierra Club analysis cited by the outlet found that US power sector emissions could rise 42 percent by 2030 as utilities add fossil fuel infrastructure to serve that demand, and Harvard researchers found that US hyperscale data centers already emit more climate pollution than Denmark.
Douglas argued that data centers would need to be supplied by newly built renewable capacity to avoid adding emissions. Matching consumption with renewable purchases, he suggested, may simply tie up limited clean power while fossil fuels fill the gap. Some environmental and humanitarian groups described this year's summit as the worst COP ever.