KEY POINTS
- Glamsterdam, once targeted for the first half of 2026, cannot reach Ethereum mainnet before mid-January 2027, according to researcher Toni Wahrstätter.
- The upgrade was given a 320-day target, while the three latest upgrades each took 433 to 475 days from scope finalization to mainnet.
- Core developers are expected to decide on Nov. 26 whether a December Hoodi testnet activation can go ahead.
Ethereum's Glamsterdam upgrade will not arrive before mid-January 2027, well after the first half of 2026 that the Ethereum Foundation had originally targeted. CryptoSlate reported that Foundation researcher Toni Wahrstätter made the assessment on Nov. 20, after delays disrupted the upgrade's testing schedule.
Wahrstätter said developers had repeatedly underestimated how long major upgrades take, even though their output has grown sharply. Monthly contributions to Ethereum's technical specifications are up between twofold and 3.5-fold since 2024. Glamsterdam also ran 12 development networks in 160 days, while Pectra needed 285 days for seven. In his words, "Nobody did a bad job, but I think we fooled ourselves, twice."
The problem, he argued, is that developers can now write specifications, code and tests faster than colleagues can review them and weigh their consequences. Glamsterdam's size makes this worse. Its execution-layer specifications run to roughly 6,080 lines, against 2,318 for Prague, the previous record. Two proposals, enshrined proposer-builder separation and block-level access lists, account for most of that bulk.
Testing demands are also heavy. EIP-8037, which changes how Ethereum charges for creating new state, has about 1,700 lines of specification but needs around 30,000 lines of tests, more than any other proposal in the upgrade.
Historical data shows the schedule was ambitious. Every upgrade since Dencun has taken more than 400 days from finalizing scope to mainnet, and the three most recent took between 433 and 475 days despite a smaller scope. Glamsterdam was given 320 days. Almost every upgrade with an announced target has missed it, with Fusaka the exception, and only after the Ethereum Object Format was removed.
Unlike earlier upgrades, Glamsterdam did not see its scope cut. Developers kept adding proposals to test environments, so it reached public testing before its specification was stable. Upgrades from Altair to Deneb recorded no specification changes after their first public testnet, Pectra had two and Fusaka one, but Glamsterdam logged 10 in six weeks. Activity on related client work rose 34% after the Sepolia activation, with client commits up 25%.
Security researchers then found problems with EIP-8037 and EIP-8038, which alter how certain operations are charged and could upset assumptions in existing smart contracts. That led developers to postpone the Oct. 26 activation on the Hoodi testnet. The gap between first public testnet and mainnet is now expected to exceed 100 days, compared with the usual four to ten weeks.
At their Nov. 19 meeting, developers tentatively aimed for Hoodi testing on Dec. 16 or 17, with mid-January 2027 as the earliest mainnet date if the specification does not change. Wahrstätter urged teams to base targets on past performance and set firm cutoffs for dropping unfinished features. He added, "I'm sure we can ship faster, but for that, we must ship smaller." Core developers are expected to decide on Nov. 26 whether the December Hoodi activation can proceed.